LPT equality cases and fixed-job performance ratios
LPT schedules the longest remaining job on a machine with the smallest current load. Its performance is measured by the last finishing time, called the makespan, divided by the optimal makespan. Graham’s worst-case factor is known exactly. The question here concerns alternative proofs of its equality cases and whether fixing the number of jobs creates a strict gap below that factor.
Why it matters and what counts as progress
Why it matters: A ratio can fail to be attained while remaining the supremum, because increasingly small positive jobs can approach an extremal instance. Keeping those notions separate matters when interpreting scheduling guarantees for a fixed job count.
What counts as progress: Give a central alternative proof, characterize all equality cases under exact processing-time assumptions, or determine the least upper bound at a fixed number of jobs.
How the problem developed
- 1969 · Optimal approximation factor [1]
Ronald L. Graham Established the LPT factor and its 2m+1-job tight family.
- 2004 · Equality characterization [2]
György Dósa Characterized the tight family. Remark 1 additionally asserted a strictly smaller supremum for every other fixed job count; the later small-positive-job construction corrects that assertion above .
Claude directed by JD Jones Supplied counting proofs of the classical bound and equality theorem, and proved the same supremum for every fixed by appending small positive jobs. The source records completed Lean checks and corrected earlier statement-description mismatches.
Follow new AI contributions to this problem.
How the problem developed
AI Proof Watch
LPT equality cases and fixed-job performance ratios
References
- [1]Graham’s original LPT bound and tight instance
- [2]Dósa’s equality theorem and fixed-job Remark 1
- [3]New counting proofs and small-job limiting construction
- [4]Completed final-tree checking and exact coverage
- [5]Model roles and corrected statement descriptions
AI contribution
A counting proof of LPT tightness and the fixed-job supremum
For independent jobs on m identical machines, the source gives counting proofs of Graham’s LPT bound and Dósa’s equality characterization, covering every tie-breaking. LPT assigns jobs in nonincreasing length order to a least-loaded machine. For and strictly positive real job lengths, equality occurs exactly for positive rescalings and reorderings of Graham’s 2m+1-job instance. For every fixed , the supremum of the LPT-to-optimal makespan ratio is still , approached by appending small positive jobs. For this supremum is not attained.
Sources
- Graham’s original LPT bound and tight instance
- Dósa’s equality theorem and fixed-job Remark 1
- New counting proofs and small-job limiting construction
- Completed final-tree checking and exact coverage
- Model roles and corrected statement descriptions
- Exact scheduling definitions, equality and fixed-n supremum
- Della Croce–Scatamacchia: later LPT bounds and earlier-source restatements