LPT equality cases and fixed-job performance ratios

LPT schedules the longest remaining job on a machine with the smallest current load. Its performance is measured by the last finishing time, called the makespan, divided by the optimal makespan. Graham’s worst-case factor is known exactly. The question here concerns alternative proofs of its equality cases and whether fixing the number of jobs creates a strict gap below that factor.

Why it matters and what counts as progress

Why it matters: A ratio can fail to be attained while remaining the supremum, because increasingly small positive jobs can approach an extremal instance. Keeping those notions separate matters when interpreting scheduling guarantees for a fixed job count.

What counts as progress: Give a central alternative proof, characterize all equality cases under exact processing-time assumptions, or determine the least upper bound at a fixed number of jobs.

How the problem developed

  1. 1969 · Optimal approximation factor [1]

    Ronald L. Graham Established the LPT factor 4/3−1/(3m)4/3-1/(3m) and its 2m+1-job tight family.

  2. 2004 · Equality characterization [2]

    György Dósa Characterized the tight family. Remark 1 additionally asserted a strictly smaller supremum for every other fixed job count; the later small-positive-job construction corrects that assertion above 2m+12m+1.

  3. 18 Oct 2026 · Counting reconstruction and supremum correction [3][4][5]

    Claude directed by JD Jones Supplied counting proofs of the classical bound and equality theorem, and proved the same supremum for every fixed n≥2m+1n\ge 2m+1 by appending small positive jobs. The source records completed Lean checks and corrected earlier statement-description mismatches.

Follow new AI contributions to this problem.

Get email updates

Download problem history

AI contribution

A counting proof of LPT tightness and the fixed-job supremum

For independent jobs on m identical machines, the source gives counting proofs of Graham’s LPT bound 4/3−1/(3m)4/3-1/(3m) and Dósa’s equality characterization, covering every tie-breaking. LPT assigns jobs in nonincreasing length order to a least-loaded machine. For m≥2m\ge 2 and strictly positive real job lengths, equality occurs exactly for positive rescalings and reorderings of Graham’s 2m+1-job instance. For every fixed n≥2m+1n\ge 2m+1, the supremum of the LPT-to-optimal makespan ratio is still 4/3−1/(3m)4/3-1/(3m), approached by appending small positive jobs. For n>2m+1n>2m+1 this supremum is not attained.

AI involvementAI-led
ImportanceModest
Technical verificationFormal (Lean)
Human understandingFew
Reported

Sources

  1. Graham’s original LPT bound and tight instance
  2. Dósa’s equality theorem and fixed-job Remark 1
  3. New counting proofs and small-job limiting construction
  4. Completed final-tree checking and exact coverage
  5. Model roles and corrected statement descriptions
  6. Exact scheduling definitions, equality and fixed-n supremum
  7. Della Croce–Scatamacchia: later LPT bounds and earlier-source restatements